An updated schedule letter has been posted regarding the construction in the Dale Avenue area. Here are the highlights:
- Week of 8/7 – Remaining concrete/curb work (except Dale Ave.)
- Week of 8/14 – Tolerancing and first lift bituminous pavement
- Week of 8/21 – Boulevard restoration and backfilling of yards
- Early/Mid September – Dale Avenue reconstruction (dependent on builders schedule)
- Mid-September – Final lift of bituminous pavement, project-wide
- Mid/Late September – Final Boulevard restoration and seed/sod, project-wide